skip to main content

S. 284 (113th): Fort Sumner Project Title Conveyance Act


The text of the bill below is as of Feb 12, 2013 (Introduced).


II

113th CONGRESS

1st Session

S. 284

IN THE SENATE OF THE UNITED STATES

February 12, 2013

(for himself andMr. Heinrich) introduced the following bill; which was read twice and referred to theCommittee on Energy and Natural Resources

A BILL

To transfer certain facilities, easements, and rights-of-way to Fort Sumner Irrigation District, New Mexico.

1.

Short title

This Act may be cited as the Fort Sumner Project Title Conveyance Act .

2.

Definitions

In this Act:

(1)

District

The termDistrictmeans the Fort Sumner Irrigation District, located in De Baca County, New Mexico.

(2)

Forbearance agreement

The termForbearance Agreementmeans the contract between the United States and the District for the forbearance of exercising priority water rights numbered 08–WC–40–292 and dated August 21, 2009 (including any amendments to that contract).

(3)

Project

The termProjectmeans the Fort Sumner reclamation project.

(4)

Repayment contract

The termRepayment Contractmeans the contract between the United States and the District numbered Ilr–1524 and dated November 5, 1948 (including any supplements and amendments to that contract).

(5)

Secretary

The termSecretarymeans the Secretary of the Interior.

(6)

Memorandum of agreement

The termMemorandum of Agreementmeans the agreement entitledMemorandum of Agreement between the United States and the Fort Sumner Irrigation District Concerning Principles and Elements of Proposed Transfer of Title to Fort Sumner Irrigation District Facilitiesand numbered 11–WC–40–406 (including any amendments to that agreement).

(7)

Transfer agreement

The termTransfer Agreementmeans the agreement between the United States and the Fort Sumner Irrigation District that identifies the specific terms and conditions of the title transfer. This document will be completed after the requirements described insection 3(d)are satisfied.

3.

Conveyance

(a)

In general

TheSecretaryis authorized to convey to the District all right and title of the United States in and to all works, land, and facilities of the Project, in accordance with the terms and conditions established in the Transfer Agreement.

(b)

Valid existing rights

The conveyance under this section shall be subject to all valid existing leases, permits, rights-of-way, easements, and other rights appurtenant to the property conveyed.

(c)

Costs of conveyance

The costs of the conveyance under this section, including the costs of environmental compliance, may be shared between the United States and the District, in accordance with the Memorandum of Agreement.

(d)

Compliance with environmental laws

(1)

In general

Before carrying out the conveyance undersubsection (a), theSecretaryshall assure compliance with all applicable requirements under—

(A)

the National Environmental Policy Act of 1969(42 U.S.C. 4321 et seq.);

(B)

the Endangered Species Act of 1973(16 U.S.C. 1531 et seq.); and

(C)

any other law applicable to the property conveyed.

(2)

Effect

Nothing in this Act modifies or alters any obligation under—

(A)

the National Environmental Policy Act of 1969(42 U.S.C. 4321 et seq.); or

(B)

the Endangered Species Act of 1973(16 U.S.C. 1531 et seq.).

(e)

Failure To convey

If theSecretaryfails to complete the conveyance under this section by the date that is 2 years after the date of completion of the requirements described insubsection (d), theSecretaryshall submit toCongressa report that—

(1)

explains the reasons why the conveyance has not been completed; and

(2)

states the date by which the conveyance will be completed.

4.

Liability

(a)

In general

Effective on the date of the conveyance undersection 3, the United States—

(1)

shall have no further interest in, and shall have no responsibility for operating or maintaining, the Project; and

(2)

shall not be liable for damages of any kind arising out of any act, omission, or occurrence relating to the conveyed property, except for damages caused by acts committed by the United States or employees, agents, or contractors of the United States before the date of the conveyance.

(b)

Effect of section

Nothing in this section increases the liability of the United States beyond the liability provided under chapter 171 of title 28, United States Code(commonly known as the Federal Tort Claims Act ).

5.

Termination of repayment contract

Effective beginning on the date of the conveyance undersection 3

(1)

the Repayment Contract shall terminate; and

(2)

the United States and the District shall have no obligations under the Repayment Contract.

6.

Forbearance agreement

(a)

Payment obligation

In accordance with paragraph 4(a) of the Forbearance Agreement, effective beginning on the date of termination of the Repayment Contract undersection 5, the United States shall have no payment obligation under paragraph 4(a) of the Forbearance Agreement.

(b)

Other terms and conditions

All other terms and conditions of the Forbearance Agreement shall remain in full force and effect on termination of the Repayment Contract undersection 5.

(c)

Term

The term of the Forbearance Agreement shall be not less than 10 years after the date of enactment of this Act, as set forth in the Memorandum of Agreement.

7.

Future benefits

After conveyance of title under this Act—

(1)

the conveyed property shall not be considered to be a part of a Federal reclamation project; and

(2)

the entity to which the property is conveyed shall not be eligible to receive any benefits, including Federal project power, with respect to the conveyed property, except for benefits that would be available to a similarly situated entity with respect to property that is not part of a Federal reclamation project.