H.R. 4411 (114th): To extend the deadline for commencement of construction of a hydroelectric project.


We don’t have a summary available yet.

The summary below was written by the Congressional Research Service, which is a nonpartisan division of the Library of Congress, and was published on Mar 14, 2016.


(This measure has not been amended since it was introduced. The summary has been expanded because action occurred on the measure.)

(Sec. 1) This bill authorizes the Federal Energy Regulatory Commission (FERC) to extend by six years the time period during which Jordan Hydroelectric Limited Partnership is required to commence construction on the Gathright Hydroelectric Project located in Alleghany County, Virginia.

In addition, FERC is authorized to reinstate the construction license if it is expired.