H.R. 2883 (115th): Promoting Cross-Border Energy Infrastructure Act

H.R. 2883 replaces the Presidential Permit process, established through executive order, with a uniform and transparent process to authorize the construction, connection, operation, and maintenance of international border-crossing facilities for the import and export of oil and natural gas and the transmission of electricity. Specifically, the bill authorizes the Federal Energy Regulatory Commission (FERC) to issue a certificate of crossing for border-crossing facilities consisting of oil or natural gas pipelines and the Secretary of Energy for border-crossing facilities of electric transmission facilities if it is within the public interest of the United States.

Executive permission in the form of a Presidential Permit is currently required for the construction, connection, operation, and maintenance of certain facilities that cross the borders between the United States with Canada and Mexico. The Department of State, the Department of Energy, and the Federal Energy Regulatory Commission participate in the review processes for cross-border energy infrastructure. The State Department makes its decisions pursuant to Executive Order 11423, as amended by E.O. 13337. FERC and the Department of Energy make permitting decisions in accordance with E.O. 10485, as amended by E.O. 12038. Each executive order requires the respective federal agency to gather necessary project specific information from an applicant, seek input from specific outside federal agencies, and decide whether to seek input from additional state, local, tribal, or federal agencies or from members of the public. Each E.O. directs the agency to issue a Presidential Permit if after evaluating all relevant project information, the agency determines the project would “serve the national interest” or “be consistent with public interest”.

Past applications for Presidential Permits have been for pipelines or transmission lines that extend a relatively short distance into a U.S. border state. Recently, Enbridge Energy’s Alberta Clipper and TransCanada’s Keystone and Keystone XL pipeline have involved projects that are hundreds of miles long and cross multiple states. It was the larger scope of such projects that, in part, resulted in increased national attention to the most recent proposal, the Keystone XL pipeline. In 2015, the State Department under President Obama denied TransCanada’s application for a Presidential Permit Presidential Permit Review for Cross-Border Pipelines and Electric Transmission Congressional Research Service for the project, finding that it did not serve the national interest. However, a new permit application was approved on March 23, 2017, when the State Department, under the Trump Administration, found that the project did serve the national interest.

Last updated Oct 3, 2017. Source: Republican Policy Committee

The summary below was written by the Congressional Research Service, which is a nonpartisan division of the Library of Congress, and was published on Jul 19, 2017.


Promoting Cross-Border Energy Infrastructure Act

(Sec.2)This bill prohibits any person from constructing, connecting, operating, or maintaining a border-crossing facility for the import or export of oil, natural gas, or electricity across an international border of the United States without obtaining a certificate of crossing.

The Federal Energy Regulatory Commission (FERC), with respect to oil or natural gas pipelines, or the Department of Energy (DOE), with respect to electric transmission facilities, must issue a certificate of crossing for the border-crossing facility within 120 days after final action is taken under the National Environmental Policy Act of 1969, unless it is not in the public interest.

DOE, as a condition of issuing a certificate, must require that the border-crossing facility be constructed, connected, operated, or maintained consistent with specified policies and standards of: (1)the Electric Reliability Organization and applicable regional entity, and (2)the Regional Transmission Organization or Independent System Operator with operational or functional control over the border-crossing facility.

The bill amends the Natural Gas Act to require FERC to approve within 30 days after receipt any application for the importation or exportation of natural gas to or from Canada or Mexico.

No presidential permit as required under specified executive orders shall be necessary for the construction, connection, operation, or maintenance of an oil or natural gas pipeline or electric transmission facility, including any border-crossing facility.

No certificate of crossing shall be required for a modification to an existing facility that is operating for the import or export of oil, natural gas, or electricity prior to the enactment of this bill.

FERC and DOE must publish a final rule in the Federal Register within one year to carry out the requirements of this bill.